G99 G100 Export Limitation: The Add-On Battery Scenario
G99 G100 export limitation becomes the central question the moment a home with existing solar adds a grid-connected battery. In the worked scenario here — 3.68 kW of registered panels plus a 2.5 kW AC storage unit — aggregate registered capacity reaches 6.18 kW per phase, above the G98 line, so pre-installation approval replaces the notify-after route plug in solar uses.
This guide follows that add-on journey end to end: the SGI routes, the paperwork, the waiting, and what an export limitation scheme genuinely controls. It is a different world from plug in solar, where a compliant kit simply notifies after installation.

Why does 3.68 kW of solar plus 2.5 kW of storage leave G98 behind?
G98's connect-and-notify route covers small generation up to 16A per phase — about 3.68 kW on a single-phase supply. A lone 2.5 kW battery fits comfortably, and a plug in solar kit at 800W fits even more easily. The problem is arithmetic: registered capacities at the same property are summed.
UK connection guidance works the example plainly: existing PV registered at 3.68 kW, plus the Anker SOLIX Solarbank 4 E5000 Pro on its own AC connection at 2.5 kW, gives 6.18 kW of aggregate registered capacity per phase. That is G99 territory, and G99 means applying before the new equipment is installed — the opposite of plug in solar timing.
Why household consumption cannot offset registered capacity
Even a household that instantly consumes every watt still has 6.18 kW registered. Instantaneous load does not shrink the installed figure the DNO assesses. Battery energy in kWh is not AC power in kW either — the 5,024Wh cell says nothing about the connection application. The same discipline applies to plug in solar: an 800W kit added to existing panels counts toward the aggregate too, despite the plug in solar framework's simpler notification flow.
Is adding battery to existing solar G99 or G98 territory?
For anyone adding battery to existing solar, G99 applies whenever the combined registered capacity crosses 16A per phase — but that does not automatically mean the full conventional application. G99 contains three Small Generation Installation processes, and the two simplified ones can fit this scenario, unlike plug in solar notification.
Keep three different numbers apart throughout. Registered capacity is the paperwork figure: 3.68 + 2.5 = 6.18 kW. Actual combined output at a given moment might be, say, 6.00 kW. Net export is output minus household use: 6 kW generated while the home draws 4 kW leaves roughly 2 kW flowing out. An export limit constrains the third number, not what the home can consume — and zero export is not the same as off-grid.
None of these subtleties arise for a stand-alone plug in solar kit, which is why plug in solar advice cannot be stretched to cover an add-on storage project.
Which SGI route fits the G99 application UK networks will assess?
SGI stands for Small Generation Installation. Any G99 application UK DNOs receive for a small system is routed through one of three processes: SGI-1 is a notification path and is not available when aggregate registered capacity exceeds 16A per phase — so it is ruled out at 6.18 kW. SGI-2 and SGI-3 are simplified pre-install applications, often called fast track; neither is automatic approval or plug in solar self-notification.
Route |
Capacity conditions |
Export limitation requirement |
Forms sequence |
SGI-1 |
Aggregate registered capacity within 16A per phase |
Not the route for this 6.18 kW scenario |
Notification path, not available here |
SGI-2 |
Each unit registered within 16A; aggregate within the 7.36 kW (32A) per-phase boundary |
Fully type-tested G100 CLS limiting net export to 3.68 kW per phase |
A1-2 + G100 Form A, then A3-2 + G100 Form C |
SGI-3 |
Each unit design within 32A; aggregate above 3.68 and within 7.36 kW per phase, with full type-test evidence |
CLS condition exemption may be requested if the DNO accepts; above the 32A boundary a G100 CLS limiting to 7.36 kW applies |
A1-2, then A3-2 (G100 forms only if a CLS is used) |
For the 6.18 kW example, both simplified routes are candidates. SGI-2 suits a project that already has a complete, compliant limitation scheme; the guidance notes DNOs generally run simpler checks than SGI-3 under §6.2.2.3(c). SGI-3 suits a project hoping the DNO will accept full output without extra limitation. The simplified route ends at a 60A aggregate boundary; exact behaviour at the 32A and 60A edges should be confirmed with the DNO, since overview tables and standard text differ on inclusivity.
A plug in solar kit never enters this table — plug in solar notification is a separate, capped regime — which is why an installer, not the householder, must choose and submit the route here.
What does G99 G100 export limitation control at the connection point?
G100 governs customer limitation schemes: a G100 export limitation caps net export at the connection point — the maximum export limit (MEL) — and can also cap net import (MIL). UK connection guidance stresses that MEL and MIL are defined as agreed maximum current per phase; the kW figures used in examples are teaching approximations, with actual limits set per phase, voltage, power factor and the approved design.
What a compliant limitation scheme involves
A compliant scheme (CLS) is a fully type-tested arrangement with fail-safe behaviour, defined tolerances, operating states and locked settings — not an app preference or a plug in solar style shortcut. It watches the whole property's flow at the connection point and acts when export approaches the agreed limit. If household load falls to 1 kW while equipment still produces 6 kW, potential export of about 5 kW must be brought back within the permitted range by the scheme's control action.
Why a 0 W app setting is not G100
Setting zero export in a monitoring app does not satisfy G100, does not cancel the G99 application, and does not prove the old PV inverter is controlled at all. A G99 G100 export limitation is evidenced hardware and scheme behaviour, verified through type tests and commissioning checks. Crucially, the Solarbank's G100 CLS scheme has not been verified — no claim should be made that it holds one; its G98 type-test listing, like the plug in solar register entry, proves nothing about limitation schemes.
Which evidence and forms does the fast track demand?
Both simplified routes require complete type-test evidence for every inverter at the property — the old PV inverter included. G98 and G99 fully-type-tested entries are both acceptable, so the storage unit's G98 register reference (ANKER/19908/V1 for the UK Solarbank model) can serve as its device evidence. A G98 number never substitutes for G100 scheme evidence, though: inverter tests and limitation-scheme tests are separate requirements, unlike the single plug in solar listing.
If the original PV paperwork cannot be found, the fast track stalls. The honest fixes are to recover the evidence, change the equipment plan, or move to a conventional G99 application — not to submit and hope. Plug in solar owners face nothing comparable, because a plug in solar kit arrives with its ENA listing as the whole evidence story.
- Installer submits Form A1-2, adding G100 Form A where a limitation scheme is used.
- DNO assesses and issues a written outcome — the proceed decision, with any conditions.
- Only then is the new unit installed and commissioned, with scheme functional and fail-safe tests where a CLS applies.
- Post-commissioning confirmation follows within 28 days: Form A3-2, plus G100 Form C when a CLS is used.
The electrical side runs in parallel: a Part P-registered electrician, a dedicated hardwired circuit and an Electrical Installation Certificate, exactly as for any storage install. The certificate goes to the owner and Building Control, not the DNO, and it never replaces the grid-connection forms.
How long does approval take, and when may installation begin?
UK connection guidance puts planned commissioning normally 10 working days to 3 months after submission for these simplified routes. The 10-working-day figure is an expectation for the assessment response — whether further study is needed — not a guarantee of approval. An automated acknowledgement is not permission.
The rule that matters most: the new unit must not be installed or commissioned before the written proceed outcome arrives. The existing PV keeps running under its own approval throughout; it is the addition that waits. If the DNO decides the local network needs study, even a capacity-compliant SGI project can be moved to the conventional process, and no plug in solar style install-first habit is permissible.
After commissioning, the 28-day confirmation window applies even if the DNO has not replied to anything else — do not let waiting for correspondence cause a missed deadline. Keep the written outcome, the confirmation and the scheme settings record with the installation certificates, a fuller file than any plug in solar owner needs after a myplugin.solar submission.
Does DNO approval mean export payments will follow?
No — connection approval and export income are separate systems. Smart Export Guarantee eligibility needs MCS certification or an accredited equivalent, half-hourly export metering, an export MPAN and a supplier's tariff terms. A written G99 outcome grants none of those, just as plug in solar registration grants none. Storage alone is not an eligible generation technology, and grid-charged electricity later exported may be treated as brown export, which suppliers are not obliged to pay for.
Anyone modifying a property that already receives SEG or Feed-in Tariff payments should ask the supplier before changing the setup, because metering and eligibility assumptions may shift. This is one more gap versus plug in solar: plug in solar kits usually cannot access SEG at all, while an add-on storage project can complicate an export arrangement that already exists.
The Anker SOLIX Solarbank 4 E5000 Pro product page documents the AC-coupling path for existing solar via the Smart Meter Gen 2, which detects surplus and charges at up to 2,500W — the technical starting point for the scenario in this guide. The Solarbank hardwired specification also confirms the 2.5 kW registered figure the application arithmetic uses.
Two boundaries close the loop. The plug in solar framework applies in Great Britain only and excludes battery storage, so this add-on scenario never qualifies for the socket route; and the plug in solar owner's duty to notify within 28 days has its counterpart here in the pre-installation G99 application, which must be approved in writing before the new unit is commissioned.
Conclusion
Adding storage to registered solar is a paperwork project before it is an electrical one: sum the registered capacities, pick the SGI route that matches the evidence, wait for the written outcome, and only then commission. G99 G100 export limitation is about controlled current at the connection point — never about an app slider or an assumed capability.
Handled in that order, the 6.18 kW scenario is routine. Handled backwards — install first, apply later — it becomes an unapproved connection, and no plug in solar analogy softens that.
Review the Anker SOLIX Solarbank 4 E5000 Pro AC-coupling specification before planning an add-on storage application.
Frequently Asked Questions
Does using all the solar at home avoid the G99 application?
No. DNOs assess aggregate registered capacity, not momentary self-consumption. A 3.68 kW array plus 2.5 kW storage stays 6.18 kW registered even when the household consumes every watt. Instantaneous load offsets net export, never the installed capacity figure the application is judged against. Plug in solar counts toward that sum too.
Is SGI-2 always the simplest route for add-on storage?
Not always. SGI-2 needs a fully type-tested limitation scheme capping net export, with its extra forms and tests. SGI-3 can avoid a scheme entirely if the DNO accepts a condition exemption. Installers should compare both against the available evidence rather than assume one route wins.
Can the old PV inverter's missing paperwork be ignored?
No. The simplified routes require complete type-test evidence for every inverter at the property, old panels included. If the original evidence cannot be recovered, the options are fixing the paperwork, changing the equipment plan, or submitting a conventional application — not proceeding as fast track.
Does export limitation restrict what the home can use?
No. A limitation scheme caps net flow at the connection point, not household consumption. With output at 6 kW and the home using 4 kW, about 2 kW exports; the home could use all 6 kW with nothing exported. Zero export also differs from off-grid operation entirely.
Can installation start while the application is being assessed?
No. The new unit must wait for the DNO's written proceed outcome before installation or commissioning; an acknowledgement email is not approval. Existing solar continues under its own approval meanwhile. After commissioning, confirmation forms are due within 28 days regardless of any pending correspondence.
Will a grid-charged battery earn export payments?
Not necessarily. Electricity stored from the grid and later exported may count as brown export, which suppliers have no obligation to pay for. Storage alone is not an eligible generation technology, and any existing export arrangement should be discussed with the supplier before the system is modified.