G98 Hardwired Solar Storage Guide: Notify, Don't Apply
This G98 hardwired solar storage guide can be summarised in one line: a registered electrician hardwires the battery, then the DNO is notified within 28 days of commissioning — no prior approval needed. Battery storage sits outside the plug in solar framework, so the socket route that plug in solar kits enjoy is not available to it.
What follows is the route map: why hardwiring is compulsory, which form the installer declares, how the paperwork differs from the plug in solar path, and which documents to keep once the confirmation lands.

Why must storage be hardwired instead of plug in solar?
UK installation guidance gives four reasons, and none of them is optional. A plug in solar kit is a compliant appliance under the 2026 plug in solar framework; a battery is a permanent generating installation, and the rules treat the two differently.
- Fixed-wiring rules: BS 1363 plugs and sockets are intended for portable appliances, while a grid-connected storage unit is fixed wiring under BS 7671.
- Continuous load: 2.5 kW at 230 V draws about 10.9 A — close to a 13A socket's rating, and socket contacts are not designed for sustained near-full load.
- Type-test assumptions: G98 protection behaviour was verified under fixed-wiring conditions, which a plug connection does not meet.
- Local isolation: fixed installations need an accessible AC isolator beside the unit for emergency and maintenance shut-off.
What about the AC plug supplied in the box?
The Anker SOLIX Solarbank 4 E5000 Pro ships with an AC plug as a spare for the future, not for present grid connection. Until plug in solar rules extend to storage — they currently cover panels only — the unit must connect through its hardwire terminals to a dedicated circuit. The factory default 800W output rises to 2,500W only after the hardwired install, grid notification and an app unlock.
What does this G98 hardwired solar storage guide check before installation?
G98 hardwired storage qualifies for connect-and-notify because 2.5 kW stays under the 16A-per-phase ceiling, about 3.68 kW single-phase. Before work starts, the installer gathers what the notification will need.
- The MPAN — the 13-digit supply number printed on the electricity bill.
- The ENA Type Test Register entry, searchable at connect-direct.energynetworks.org/device-databases/search-gen; the Solarbank is G98 listed under reference ANKER/19908/V1.
- The registered capacity and system reference number, copied verbatim from the register.
- The consumer unit's RCD type, upgraded before installation if it is Type AC.
- The commissioning date plan — the 28-day notification window includes commissioning day itself.
Which RCD type does a storage circuit need?
UK installation guidance recommends Type A as the minimum: it detects AC and pulsating DC leakage. Type AC cannot detect smooth DC leakage from inverter faults and is not recommended; Type B covers all leakage types where the inverter manual demands it. An RCBO combines breaker and RCD — storage circuits commonly use 16A or 32A devices — and the type is identified by the printed marking on the device. The electrician also records the earthing arrangement, typically TN-C-S (PME). A plug in solar kit avoids this work because it is treated as an appliance, which is precisely why its ceiling is 800W.
How do the hardwired and plug in solar notification routes differ?
Both routes end in a G98 notification inside 28 days, but almost everything upstream differs. The comparison below is the heart of any G98 hardwired solar storage guide, because the plug in solar shortcut is routinely misapplied to batteries.
Item |
Plug in solar kit (up to 800W) |
Hardwired storage (2.5 kW) |
Who installs |
Householder, self-install |
Part P-registered electrician |
Notification form |
Form B2, completed by the householder |
Form B1, completed and declared by the installer |
Submission channel |
myplugin.solar |
DNO email or online portal |
Energy source code |
R/11 (PV only) |
R/11 + 38 with panels; S/38 grid-charged only |
Electrical certificate |
Not normally required (appliance) |
EIC required, kept by the owner |
On-site test report |
Not required — ENA register record |
Not required — ENA register record |
Cost to notify |
Free, self-service |
Free, self-service |
The form split matters: for hardwired solar storage G98 documentation ends with an installer declaration that the work complies with the engineering recommendation, so a DIY hardwired install is not defensible and risks rejection or a paid review. A plug in solar owner, by contrast, files Form B2 personally through myplugin.solar — one device per household, fixed 13A socket, no extension leads, ENA-listed kit only.
Note also what neither route needs: an uploaded on-site test report. The manufacturer's type-test record on the ENA register replaces site testing in both cases — a shared simplification that plug in solar and hardwired storage owners alike can rely on.
Which fields does the installer declare on the hardwired form?
Rather than repeat a full field-by-field walkthrough, focus on the entries where the hardwired route diverges from plug in solar. The installer declares: name, address and postcode; the 13-digit MPAN; inverter make, model and serial number from the unit label; registered capacity of 2.5 kW; the ENA system reference verbatim; total per-phase capacity (all on Phase 1 for a typical single-phase home); and the commissioning date.
Which energy source code applies?
The code follows what is actually connected, not what the device could do. Panels connected to the storage unit: R/11 + 38. Battery charged from the grid with no panels: S/38. Panels without a battery — the classic plug in solar arrangement — would be R/11. Copy the codes from the current form's code table before filing, because the DNO assesses actual grid behaviour. The current edition of the recommendation is G98 Issue 2, amended to admit compliant plug in solar devices; older guides still labelled with the 2021 amendment are out of date.
One more trap from real cases: a single-home, single-unit install needs only the installation document. Filing the batch application form as well can make the DNO treat a domestic job as a multi-premises development — an error no plug in solar filer encounters on myplugin.solar, where the flow is fixed.
Who receives the EIC, and who receives the G98 notice?
These are two separate regimes, and conflating them causes most delays. The Electrical Installation Certificate proves the fixed wiring is safe to BS 7671; it goes to the owner, Building Control and the insurer — never to the DNO. The G98 notification is the grid-compliance notice, and it goes to the DNO. G98 compliance UK households owe is a notification duty, not an approval process.
If the original contractor never issued the EIC, ask them first: issuing it is part of their job, and paying a second electrician to re-inspect their work should not be necessary. Meanwhile the G98 filing itself is free and self-service — the duty sits with the owner or operator, and because the equipment is already on the ENA register, the DNO pulls the type-test record from the registered capacity and system reference. Nobody needs to pay a filing agent for either the hardwired or the plug in solar route.
The Anker SOLIX Solarbank 4 E5000 Pro product page sets out the hardwired installation requirement and the Smart Meter Gen 2 pairing the electrician works to — useful to read before agreeing a quote, so the certificate and the notification are both priced into the job rather than treated as extras.
Which DNO gets the notice, and what should be kept afterwards?
Great Britain's distribution regions map to six DNO groups. UK installation guidance lists the portals as follows:
- London, the South East and East Anglia — UK Power Networks (ukpowernetworks.co.uk).
- North West England — Electricity North West (enwl.co.uk).
- Yorkshire and the North East — Northern Powergrid (northernpowergrid.com).
- Midlands, South West England and South Wales — National Grid Electricity Distribution; use connections.nationalgrid.co.uk, as the older address path no longer resolves.
- North Wales and Merseyside (SP Manweb) plus Central and Southern Scotland (SP Distribution) — spenergynetworks.co.uk.
- Northern Scotland and central southern England — SSEN (ssen.co.uk). Northern Ireland is served by NIE Networks under different rules, outside the plug in solar framework and this guide's scope.
When the confirmation arrives, keep the DNO's email and reference number with the purchase receipt. Insurers, smart meter teams, property buyers and Smart Export Guarantee applications can all ask for it — the same evidence trail a careful plug in solar owner builds after filing via myplugin.solar. The hardwired Solarbank specification and G98 listing is worth bookmarking alongside that paperwork, since the ENA reference on it is the one quoted on the form.
If existing rooftop solar is already registered at the property, the installer must check aggregate capacity before choosing this route: above 16A per phase the project moves to G99 pre-approval, and no plug in solar style notify-after-installing shortcut applies.
The deadline is a duty, not a courtesy: the DNO must receive the notification within 28 days of commissioning, counting the commissioning day. The plug in solar route carries the same 28-day must, filed by the owner through myplugin.solar in Great Britain.
Conclusion
The hardwired route is longer than the plug in solar route by design: an electrician, a dedicated circuit, an EIC and an installer-declared form. In exchange, storage delivers 2.5 kW of output and 5,024Wh of capacity that no plug in solar kit can legally match.
Treat this G98 hardwired solar storage guide as a sequence — install, certify, notify, retain — and the whole process costs nothing beyond the installation itself. The notify-not-approve regime is genuinely simple once the wiring is done properly.
See the Anker SOLIX Solarbank 4 E5000 Pro for the G98-listed hardwired specification this notification route applies to.
Frequently Asked Questions
Does the DNO have to approve a G98 installation before it runs?
No. G98 is connect-and-notify: the system can be commissioned first, and the DNO must receive the notification within 28 days, a window that includes commissioning day. Prior approval belongs to G99 for larger aggregate capacities. The plug in solar framework uses the same notify-after principle through myplugin.solar.
Can the homeowner submit the hardwired notification personally?
Yes. The notification duty sits with the owner or operator, filing is free and self-service, and the ENA register entry means no on-site test report is needed. The installation itself, however, must be done and declared by a registered electrician — self-filing the form never legitimises DIY hardwiring.
Is an on-site grid test report required for storage?
No. G98 replaces site testing with manufacturer type-testing. The DNO retrieves the record using the registered capacity and ENA system reference number entered on the form, so neither the electrician nor the owner uploads a test report. Plug in solar notifications work identically on this point.
Should a paid agent be hired to file the notification?
No. Filing is free for both hardwired storage and plug in solar kits, and an agent adds cost without adding compliance. Worse, the confirmation email and reference number would go to the agent rather than the owner, who needs them for insurance, property sale and export-tariff applications.
Which certificate proves the hardwiring itself is safe?
The Electrical Installation Certificate, issued by the installing electrician to BS 7671, covers the fixed wiring for the owner, Building Control and the insurer. It is separate from the G98 grid notification and is never sent to the DNO. New circuits call for a full certificate, not a minor-works one.
What paperwork applies when a storage unit is removed?
Decommissioning has its own G98 form, submitted within 28 days of removal so the DNO's records stay accurate. Keep the original installation confirmation and the decommissioning acknowledgement together with the purchase receipt. The obligation mirrors the notification discipline that plug in solar owners follow when retiring a kit.